上海某深基坑支護(hù)工程設(shè)計、監(jiān)測與數(shù)值模擬
[Abstract]:With the remarkable achievements in economic construction and reform and opening up in China, the national economy is also growing at a high speed, and a variety of large and medium-sized construction projects are springing up like bamboo shoots. As a preliminary and basic work in the field of construction, the foundation and foundation engineering has reached a completely new level in terms of investigation, design, construction and monitoring after numerous scientific and technological workers have carried out theoretical discussions and studies, and the engineering quality and safety have been reached. The time limit is optimized. However, due to the vast territory, complex geology, wide distribution, construction quality and uneven technology, there are still many problems in engineering practice, especially the safety problems make the people's lives at the disadvantage of the edge. Therefore, how to carry out the construction safely and economically on the basis of the existing theory has been placed in front of the constructors. Based on the new industrial workshop and auxiliary building (North block) engineering in Shanghai, according to the geological conditions of the site, the design plan of foundation pit support and the design data of foundation pit enclosure structure, the field monitoring scheme for foundation pit excavation during the excavation process is established in this paper. During the excavation of foundation pit, the monitoring data show that the displacement of the surrounding soil and the surrounding soil can meet the safety requirements of the excavation. Through the analysis of monitoring data and finite element calculation results, combined with the safety control requirements of foundation pit support structure, the following conclusions are obtained: (1) according to the characteristics of this project, the design and stability calculation of the selected supporting system is calculated in detail; (2) simulating and analyzing the foundation pit with MIDAS software through the survey report and related parameters, analyzing and determining the security of the selected scheme, (3) using the network monitoring points to monitor the construction process with information, (4) through the scientific comparison of simulation data and monitoring data to determine the practical significance of software analysis to construction guidance and provide reference for similar projects. Comparing with the field monitoring data, the excavation of foundation pit has a certain influence on the security of the surrounding environment, but it is within the control range. The numerical simulation results are consistent with the field monitoring rules, and the rationality of finite element numerical simulation is verified.
【學(xué)位授予單位】:天津大學(xué)
【學(xué)位級別】:碩士
【學(xué)位授予年份】:2013
【分類號】:TU473.2
【參考文獻(xiàn)】
相關(guān)期刊論文 前9條
1 曾遠(yuǎn),李志高,王毅斌;基坑開挖對鄰近地鐵車站影響因素研究[J];地下空間與工程學(xué)報;2005年04期
2 劉建航,劉國彬,范益群;軟土基坑工程中時空效應(yīng)理論與實踐(上)[J];地下工程與隧道;1999年03期
3 呂愛鐘,蔣斌松,尤春安;位移反分析有限元網(wǎng)格劃分范圍的研究[J];土木工程學(xué)報;1999年01期
4 李大勇,龔曉南;軟土地基深基坑工程鄰近柔性接口地下管線的性狀分析[J];土木工程學(xué)報;2003年02期
5 張治國;張謝東;王衛(wèi)東;;臨近基坑施工對地鐵隧道影響的數(shù)值模擬分析[J];武漢理工大學(xué)學(xué)報;2007年11期
6 張云軍,宰金珉,王旭東,戚科俊,王偉;南京地區(qū)某深基坑工程的監(jiān)測與分析[J];巖土工程界;2004年11期
7 鄧楚鍵;何國杰;鄭穎人;;基于M-C準(zhǔn)則的D-P系列準(zhǔn)則在巖土工程中的應(yīng)用研究[J];巖土工程學(xué)報;2006年06期
8 邊亦海;黃宏偉;;深基坑開挖引起的建筑物破壞風(fēng)險評估[J];巖土工程學(xué)報;2006年S1期
9 何世秀,韓高升,莊心善,吳香國;基坑開挖卸荷土體變形的試驗研究[J];巖土力學(xué);2003年01期
相關(guān)博士學(xué)位論文 前1條
1 秦昊;地鐵車站基坑開挖對鄰近地下管線的影響研究[D];中國地質(zhì)大學(xué)(北京);2010年
本文編號:2259437