基于IGDT的有源配電網(wǎng)魯棒恢復(fù)決策方法
發(fā)布時(shí)間:2019-04-04 20:19
【摘要】:由于分布式電源(distributed generator,DG)的接入,有源配電網(wǎng)運(yùn)行的不確定性顯著增大。其中,負(fù)荷需求及DG出力的不確定性對(duì)于恢復(fù)策略的制定影響顯著。為此,提出一種基于信息間隙決策理論(information gap decision theory,IGDT)的配電網(wǎng)故障下失電負(fù)荷恢復(fù)的魯棒決策模型。對(duì)于給定的不確定參數(shù)變化集,該模型給出的策略可以保證恢復(fù)結(jié)果不差于某一預(yù)設(shè)的最低可接受度。基于該模型,開發(fā)了以恢復(fù)更多失電負(fù)荷為目標(biāo)的魯棒恢復(fù)程序。最后,采用PGE 69節(jié)點(diǎn)配電網(wǎng)算例系統(tǒng)對(duì)于所提方法進(jìn)行了分析驗(yàn)證。
[Abstract]:Due to the access of distributed power supply (distributed generator,DG), the uncertainty of active distribution network operation increases significantly. Among them, the uncertainty of load demand and DG output has a significant impact on the establishment of recovery strategy. Therefore, a robust decision-making model based on information gap decision theory (information gap decision theory,IGDT) for power loss load restoration in distribution network under fault is proposed. For a given variable set of uncertain parameters, the strategy given by the model can guarantee that the recovery result is not worse than a certain preset minimum acceptability. Based on this model, a robust recovery program is developed to recover more power loss loads. Finally, an example system of PGE 69-bus distribution network is used to analyze and verify the proposed method.
【作者單位】: 電力系統(tǒng)及發(fā)電設(shè)備控制和仿真國(guó)家重點(diǎn)實(shí)驗(yàn)室(清華大學(xué)電機(jī)系);貴州電網(wǎng)公司;
【基金】:“十一五”國(guó)家科技支撐計(jì)劃重大項(xiàng)目(2013BAA01B01) 黔科重大專項(xiàng)字([2012]6022)~~
【分類號(hào)】:TM732
[Abstract]:Due to the access of distributed power supply (distributed generator,DG), the uncertainty of active distribution network operation increases significantly. Among them, the uncertainty of load demand and DG output has a significant impact on the establishment of recovery strategy. Therefore, a robust decision-making model based on information gap decision theory (information gap decision theory,IGDT) for power loss load restoration in distribution network under fault is proposed. For a given variable set of uncertain parameters, the strategy given by the model can guarantee that the recovery result is not worse than a certain preset minimum acceptability. Based on this model, a robust recovery program is developed to recover more power loss loads. Finally, an example system of PGE 69-bus distribution network is used to analyze and verify the proposed method.
【作者單位】: 電力系統(tǒng)及發(fā)電設(shè)備控制和仿真國(guó)家重點(diǎn)實(shí)驗(yàn)室(清華大學(xué)電機(jī)系);貴州電網(wǎng)公司;
【基金】:“十一五”國(guó)家科技支撐計(jì)劃重大項(xiàng)目(2013BAA01B01) 黔科重大專項(xiàng)字([2012]6022)~~
【分類號(hào)】:TM732
【參考文獻(xiàn)】
相關(guān)期刊論文 前4條
1 吳文傳,張伯明;基于待恢復(fù)樹切割的配電網(wǎng)故障恢復(fù)實(shí)時(shí)算法[J];電力系統(tǒng)自動(dòng)化;2003年12期
2 陳珂寧;吳文傳;郭昆亞;張伯明;王英男;;基于負(fù)荷恢復(fù)策略的配電網(wǎng)N-1安全評(píng)估[J];電網(wǎng)技術(shù);2013年11期
3 王增平;張麗;徐玉琴;李雪冬;;含分布式電源的配電網(wǎng)大面積斷電供電恢復(fù)策略[J];中國(guó)電機(jī)工程學(xué)報(bào);2010年34期
4 黎恒p,
本文編號(hào):2454133
本文鏈接:http://sikaile.net/kejilunwen/dianlilw/2454133.html