【摘要】:本研究對(duì)廣西的電力需求水平、電源建設(shè)規(guī)劃及電網(wǎng)發(fā)展規(guī)劃進(jìn)行了詳細(xì)的分析研究,在總結(jié)電網(wǎng)現(xiàn)況存在問(wèn)題的基礎(chǔ)上,結(jié)合廣西電網(wǎng)自身能源資源狀況、負(fù)荷需求,重點(diǎn)研究了廣西未來(lái)電力供應(yīng)保障、新建電源的布局及建設(shè)時(shí)序、電源結(jié)構(gòu)優(yōu)化、廣西500千伏和220千伏變電站和網(wǎng)架建設(shè)、電磁環(huán)網(wǎng)解環(huán)方案等方面的問(wèn)題。未來(lái)廣西電網(wǎng)在電源供應(yīng)保障方面,將貫徹深度開(kāi)發(fā)水電、優(yōu)化發(fā)展煤電、加快發(fā)展核電、合理消納西電、積極發(fā)展新能源的電源建設(shè)方針,以電源建設(shè)規(guī)劃適度超前為原則,確保廣西電力供需平衡,為廣西經(jīng)濟(jì)和社會(huì)穩(wěn)步發(fā)展提供充足的電力保障。在電網(wǎng)建設(shè)方面,將立足已建成的500千伏主網(wǎng)架,大力發(fā)展區(qū)內(nèi)輸供電網(wǎng)絡(luò)建設(shè),使廣西電網(wǎng)從目前南方電網(wǎng)“西電東送”的支撐和電源補(bǔ)充基地,逐步轉(zhuǎn)變成為南方統(tǒng)一主網(wǎng)架中另一個(gè)重要的受端電網(wǎng),以滿足廣西社會(huì)經(jīng)濟(jì)健康和快速發(fā)展的需要。將廣西電網(wǎng)建設(shè)成為“統(tǒng)一開(kāi)放、結(jié)構(gòu)合理、技術(shù)先進(jìn)、安全可靠”的現(xiàn)代化大電網(wǎng),為北部灣經(jīng)濟(jì)區(qū)開(kāi)放開(kāi)發(fā)、承接?xùn)|部產(chǎn)業(yè)轉(zhuǎn)移及鋁工業(yè)等廣西重點(diǎn)發(fā)展戰(zhàn)略用電需求提供可靠的電力支撐。
[Abstract]:This research has carried on the detailed analysis and research to the Guangxi electric power demand level, the power source construction plan and the power network development plan. On the basis of summarizing the existing problems of the power network, combined with the Guangxi power grid's own energy resource condition, the load demand, This paper focuses on the future power supply in Guangxi, the layout and construction sequence of the new power supply, the optimization of the power supply structure, the construction of 500 kV and 220 kV substations and grids in Guangxi, and the solution scheme of the electromagnetic ring network. In the future, Guangxi power grid will carry out the principle of developing hydropower in depth, optimizing the development of coal and electricity, speeding up the development of nuclear power, reasonably absorbing electricity from the west, actively developing new energy sources, and taking the power source construction plan as the principle of moderately ahead of schedule. Ensure the balance of power supply and demand in Guangxi, and provide sufficient power security for the steady development of Guangxi economy and society. In the area of power grid construction, we will base ourselves on the established 500kV main grid, vigorously develop the construction of regional transmission and power supply networks, and enable Guangxi Power Grid to support and supplement its power supply base from the current "West-to-East Power Transmission" of the Southern Power Grid. In order to meet the needs of the healthy and rapid development of Guangxi's social economy, it has gradually changed into another important receiving network in the unified main grid in the south. To build Guangxi power grid into a modern power grid with "unified opening, reasonable structure, advanced technology and safe and reliable", which is open and developed for the Beibu Gulf Economic Zone, Undertake eastern industrial transfer and aluminum industry and other key development of Guangxi strategic demand to provide reliable power support.
【學(xué)位授予單位】:廣西大學(xué)
【學(xué)位級(jí)別】:碩士
【學(xué)位授予年份】:2015
【分類號(hào)】:F426.61
【參考文獻(xiàn)】
相關(guān)期刊論文 前6條
1 梁錦照;夏清;王德興;;快速發(fā)展城市的組團(tuán)式電網(wǎng)規(guī)劃新思路[J];電網(wǎng)技術(shù);2009年17期
2 劉巍;淺談電力市場(chǎng)下電網(wǎng)規(guī)劃的基本思路[J];廣東電力;2004年01期
3 莫仕勛;吳杰康;李如琦;貝宇;;負(fù)荷預(yù)測(cè)系統(tǒng)數(shù)據(jù)缺失與畸變的分析及其處理[J];廣西大學(xué)學(xué)報(bào)(自然科學(xué)版);2010年02期
4 鐘杰峰;廣東電力彈性系數(shù)變化趨勢(shì)分析[J];華東電力;2000年10期
5 錢(qián)紋;采用電力彈性系數(shù)法預(yù)測(cè)負(fù)荷[J];云南電力技術(shù);2001年01期
6 朱成章;單位產(chǎn)值電耗和電力彈性系數(shù)[J];中國(guó)能源;1994年06期
,本文編號(hào):1890873
本文鏈接:http://sikaile.net/kejilunwen/dianlilw/1890873.html
最近更新
教材專著