中山市東區(qū)10kV配電網(wǎng)的可靠性評估與優(yōu)化
[Abstract]:With the acceleration of urbanization in China, the demand for reliability of power supply is becoming higher and higher. Power outages have also been shortened from hours to minutes or even uninterrupted power. As the end of the power supply system, the distribution network plays the role of docking with the user and the last kilometer. The reliability of distribution network directly affects the feeling of power consumption and the evaluation of power grid. Therefore, how to improve the reliability of distribution network has become a problem we must face. As the center of Pearl River Delta, Zhongshan City is the vanguard of Guangdong Power Grid, which has higher demand for power supply reliability. As the city center of Zhongshan City, East District is the background of this paper, how to improve the reliability of distribution network at a high level. First of all, through the analysis of the substation, 10kV distribution network structure and 10kV distribution equipment in the eastern district of Zhongshan City, the basic situation and present situation of the distribution network in the eastern district are evaluated. It provides the basic data basis for the research and achieves the preliminary purpose of the research. Secondly, by analyzing the reliability data of the eastern region in 2015 and 2016, the paper finds out the key factor that affects the reliability of the eastern power distribution network, that is, the fault blackout. According to the analysis of the failure power failure, combined with the reliability data of the eastern region in recent years, The reliability of eastern distribution network is evaluated, and the main reasons of power outage are transformer fault, cable fault, equipment aging fault and so on. The reliability of eastern distribution network is comprehensively evaluated. Finally, the Bayesian method is used to analyze and optimize the reliability of the eastern distribution network and its improvement measures. According to the corresponding fault points, the solutions are made, such as low voltage loop network, voltage monitoring, building new station area, strengthening the automation construction of distribution network and so on, so as to provide reference for the future distribution network construction and network structure reconstruction. The reliability of the eastern distribution network can be further improved. The reliability of 2017 is forecasted by grey forecast method, and compared with the target of 2012-2016. I believe that through the implementation of these measures, Eastern distribution network reliability will be a big leap forward.
【學(xué)位授予單位】:吉林大學(xué)
【學(xué)位級別】:碩士
【學(xué)位授予年份】:2017
【分類號】:TM732
【參考文獻(xiàn)】
相關(guān)期刊論文 前10條
1 任遠(yuǎn);史添;;優(yōu)化配電網(wǎng)網(wǎng)架,促進(jìn)城市發(fā)展[J];電子測試;2016年08期
2 毛興宇;;影響城市供電網(wǎng)系統(tǒng)可靠性的原因分析[J];科技經(jīng)濟(jì)市場;2016年03期
3 郭世明;;電力系統(tǒng)配電網(wǎng)自動(dòng)化的應(yīng)用探討[J];科學(xué)中國人;2015年36期
4 王哲;羅鳳章;竺笠;翟瑋;;中壓配電網(wǎng)接線模式分段和聯(lián)絡(luò)優(yōu)化配置方法[J];電力系統(tǒng)及其自動(dòng)化學(xué)報(bào);2015年S1期
5 閻波;;電力系統(tǒng)及其自動(dòng)化技術(shù)的應(yīng)用探討[J];經(jīng)營管理者;2015年29期
6 張航;;電力系統(tǒng)配電網(wǎng)自動(dòng)化實(shí)現(xiàn)技術(shù)探索[J];電子技術(shù)與軟件工程;2015年06期
7 易太和;;探討電力系統(tǒng)自動(dòng)化技術(shù)的運(yùn)用與發(fā)展[J];通訊世界;2014年08期
8 周勇;;探討提高電力配網(wǎng)可靠性的技術(shù)措施[J];低碳世界;2013年16期
9 陳福軍;楊勇;;提高電力配網(wǎng)可靠性的技術(shù)措施分析[J];廣東科技;2013年10期
10 蔡澤祥;周全;;配網(wǎng)接線方式對供電可靠性影響分析[J];電力系統(tǒng)及其自動(dòng)化學(xué)報(bào);2010年04期
相關(guān)博士學(xué)位論文 前3條
1 劉壯志;含微電網(wǎng)的智能配電網(wǎng)規(guī)劃理論及其應(yīng)用研究[D];華北電力大學(xué);2013年
2 袁明軍;配電系統(tǒng)可靠性評估方法與應(yīng)用研究[D];山東大學(xué);2011年
3 謝瑩華;配電系統(tǒng)可靠性評估[D];天津大學(xué);2005年
相關(guān)碩士學(xué)位論文 前3條
1 黃宇峰;城市中壓配電網(wǎng)可靠性快速評估及預(yù)測方法的研究[D];華北電力大學(xué)(北京);2011年
2 陳興雷;配電網(wǎng)可靠性與經(jīng)濟(jì)性綜合評估[D];浙江大學(xué);2008年
3 牛雪媛;配電網(wǎng)可靠性研究及應(yīng)用[D];鄭州大學(xué);2004年