盾構隧道垂直下穿既有管線的擾動效應研究
[Abstract]:The influence of shield tunneling on the surrounding environment has become an important research topic, in which the influence of shield tunneling on the surrounding pipeline is particularly prominent. At present, there is still a weak link in the study of the influence of shield tunnel on the surrounding pipeline, and most of the studies only consider the influence of a single factor on the pipeline deformation. In this paper, sensitivity analysis of the main factors affecting pipeline displacement is carried out, which provides a reference for the design and construction of practical engineering. Based on the theory of elastic foundation beam, the deformation mechanism of stratum and pipeline caused by tunnel construction is discussed. The mechanical effect of rigid interface pipeline and flexible interface pipeline subjected to vertical perturbing disturbance of tunnel is analyzed, and the prediction method of pipeline deformation and force is put forward. By using FLAC3D finite difference numerical simulation combined with the measured results, the law of pipeline and surface subsidence in two-line tunnel construction is comprehensively analyzed: after the construction of the left tunnel, the lateral settlement trough and the displacement curve of the pipeline conform to Gao Si's distribution. The maximum settlement of pipeline and surface is directly above the center of left tunnel. After the excavation of the right-line tunnel, the main settlement range of the surface and pipeline becomes larger. The settlement characteristics of the surface approximately accord with Gao Si distribution, the settlement is larger than that of the left tunnel, the center settlement curve of the two tunnels is relatively gentle, and the maximum settlement changes between the two tunnels. The settlement of pipeline is "one peak and two valleys", which does not accord with Gao Si distribution, and the maximum settlement value of pipeline is close to the left tunnel. The influence of six main factors on pipeline settlement is studied by numerical simulation. With the increase of tunnel tunneling speed and tunnel diameter, the vertical displacement and maximum settlement of pipeline become larger with the depth of overburden of pipeline, tunnel tunneling rate and tunnel diameter. The vertical displacement and maximum settlement of the pipeline gradually decrease with the increase of the diameter of pipeline, the pressure ratio of excavated surface support and the distance between pipes and tunnels, and the main settlement range of pipeline increases with the increase of tunneling speed and diameter. The maximum settlement of pipeline is linearly related to the depth of overlying soil, the ratio of support pressure to excavating surface, and the diameter of tunnel. Taking the maximum settlement of pipeline as the index and adopting the method of grey correlation analysis, the influence sensitivity of each factor is compared and studied. The order of sensitivity to the influence of pipeline settlement from strong to weak is: tunnel diameter, tunnel spacing, pipeline diameter, and so on. Pipeline overlying depth, excavating surface support pressure ratio, tunneling rate.
【學位授予單位】:太原理工大學
【學位級別】:碩士
【學位授予年份】:2017
【分類號】:U455.43;TU990.3
【參考文獻】
相關期刊論文 前10條
1 魏綱;周楊侃;;隨機介質(zhì)理論預測近距離平行盾構引起的地表沉降[J];巖土力學;2016年S2期
2 王春梅;何越磊;汪磊;李培超;;隧道下穿引起地下管線豎向位移的計算方法研究[J];隧道建設;2016年02期
3 任艷榮;王少欽;;基于Abaqus軟件盾構法隧道施工下的市政管線的動力分析[J];建筑技術;2016年02期
4 孫金澤;;盾構法施工技術的研究現(xiàn)狀與發(fā)展前景[J];建筑技術開發(fā);2015年03期
5 梁榮柱;夏唐代;林存剛;俞峰;;盾構推進引起地表變形及深層土體水平位移分析[J];巖石力學與工程學報;2015年03期
6 王夢恕;;中國盾構和掘進機隧道技術現(xiàn)狀、存在的問題及發(fā)展思路[J];隧道建設;2014年03期
7 谷拴成;李敏;;西安地鐵盾構施工地表沉降隨機介質(zhì)預測研究[J];鐵道工程學報;2014年03期
8 劉思峰;蔡華;楊英杰;曹穎;;灰色關聯(lián)分析模型研究進展[J];系統(tǒng)工程理論與實踐;2013年08期
9 張陳蓉;俞劍;黃茂松;;隧道開挖對鄰近非連續(xù)接口地埋管線的影響分析[J];巖土工程學報;2013年06期
10 劉宣宇;;盾構技術的發(fā)展與展望[J];施工技術;2013年01期
相關會議論文 前1條
1 李春生;;灰色推廣學[A];第16屆全國灰色系統(tǒng)學術會議論文集[C];2008年
相關博士學位論文 前4條
1 楊茜;盾構隧道縱向不均勻沉降及實時監(jiān)測方法研究[D];北京交通大學;2013年
2 賈勇;盾構施工地層變形實測與三維數(shù)值模擬及參數(shù)分析[D];天津大學;2010年
3 吳為義;盾構隧道周圍地下管線的性狀研究[D];浙江大學;2008年
4 秦建設;盾構施工開挖面變形與破壞機理研究[D];河海大學;2005年
相關碩士學位論文 前8條
1 陳俊羽;盾構隧道施工對既有管線的影響研究[D];廣西大學;2016年
2 張倫政;地下管線與土層相互作用數(shù)值模擬與離心模型試驗研究[D];北京交通大學;2014年
3 王雨;地鐵隧道施工對地下管線變形的影響研究[D];北京交通大學;2014年
4 邱明明;城市地鐵隧道盾構施工引起的地層變形預測研究[D];南昌航空大學;2013年
5 孫玉剛;灰色關聯(lián)分析及其應用的研究[D];南京航空航天大學;2007年
6 曹明霞;灰色關聯(lián)分析模型及其應用的研究[D];南京航空航天大學;2007年
7 楊俊濤;垂直荷載作用下埋地管道的縱向力學性狀分析[D];浙江大學;2006年
8 馬濤;隧道施工引起的地層位移及其對鄰近地下管線的影響分析[D];長沙理工大學;2005年