天堂国产午夜亚洲专区-少妇人妻综合久久蜜臀-国产成人户外露出视频在线-国产91传媒一区二区三区

當前位置:主頁 > 科技論文 > 路橋論文 >

隧道出口明挖段深基坑施工過程中的變形及穩(wěn)定性研究

發(fā)布時間:2018-09-18 20:34
【摘要】:就基坑工程在開挖過程中的內力和變形規(guī)律,巖土工作者已做了大量的研究,但對于狹長型基坑在開挖過程中基坑受力、變形機理的實測和分析卻較少。隨著我國大規(guī)模的進行城市軌道建設,這類型基坑會大量遇到,對此類基坑在開挖過程中的受力和變形機理進行研究探討,可以為以后類似工程的設計和施工積累經驗。在閱讀大量國內外相關文獻,總結相關研究成果的基礎上。本文以哈爾濱到牡丹江客運專線(哈牡客專)愛民隧道出口明挖段狹長型深基坑在開挖過程中的現場監(jiān)測為依托,結合理論分析及三維數值模擬分析,指導現場施工、反饋設計的同時對本地區(qū)狹長基坑在開挖過程中圍護結構的受力、變形以及開挖對周邊環(huán)境的影響進行了初步探討。最后,通過三維數值模擬分析的方法對圍護結構參數進行了多方位優(yōu)化,為工程后續(xù)施工以及本地區(qū)類似基坑工程設計、施工提供參考。本文主要內容及相關結論如下:(1)通過現場監(jiān)測可知,基坑施工全過程中,各監(jiān)測項目的量均未達到報警值,圍護結構正常工作;訌拈_挖暴露到底板施做完畢全過程中,樁身水平位移最大值達到13.72mm,位于撐間樁上距樁頂往下8.0m左右處,位置隨著最大值增加不斷下移,剛開挖到底時最大值在距樁頂7.0m左右處;樁身彎矩最大值也發(fā)生在撐間樁上,最大值達到了464.0kN.m,與樁身正截面抗彎承載力1410kN.m相距甚遠,究其原因,是由于現場實測得到的樁頂和樁底均發(fā)生了一定量的水平位移,這樣勢必會對圍護樁的內力產生一定的釋放作用;現場實測得到的橫撐和冠梁位移及受力均處于較小狀態(tài)。(2)對比現場實測、三維有限元分析及規(guī)范法得到的樁身水平位移,規(guī)范法得到的值最大,最大值達到了16.78mm,最大值發(fā)生位置與三維有限元分析得到的最大值位置一致,發(fā)生在距樁頂7.5m左右處,現場實測得到的最大值位置略微向下,位于距樁頂8.0m左右處;對樁身彎矩而言,三維有限元分析下的最大值為883.1kN.m,規(guī)范法計算的最大值為966.5kN.m,現場實測結果卻小很多,最大值只有464.0kN.m,由內里釋放引起;冠梁的內力及變形三種方法得到的結果大小與趨勢均較接近。(3)為了綜合評價基坑的穩(wěn)定性,通過經驗公式和三維有限元分析對地表沉降和坑底隆起進行估算。經驗公式得到的地表沉降最大值為10.7mm,發(fā)生在距樁頂6.9m處;三維有限元分析得到的地表最大沉降為11.2mm,距樁頂6.5m處;經驗公式得到的坑底隆起最大值為10.2mm,三維有限元分析得到的坑底隆起最大值為12.1mm,發(fā)生在距離圍護結構約1.0m處。(4)各優(yōu)化方案中,改變錨固段長度對圍護結構的受力及變形影響均最小;改變樁徑對圍護樁及橫撐的影響最為劇烈,當樁徑從1.0m減小到0.7m時,水平位移最大值達到28.0mm,與30mm的報警值已非常接近,樁身彎矩已達到了樁身正截面彎矩承載力的85.4%,此時橫撐彎矩相較原模型增大了139%,已經超過了橫撐正截面抗彎承載力815kN.m;冠梁彎矩卻是對樁間距的改變最為敏感,但是在整個優(yōu)化過程中,冠梁彎矩均處于較小狀態(tài)。最后提出一種適用于按照現場施工工序施工的圍護結構設計方案,此方案在保證施工安全的前提下,經濟合理。
[Abstract]:Geotechnical workers have done a lot of research on the internal force and deformation law of foundation pit engineering in the excavation process, but there are few measurement and Analysis on the deformation mechanism of the narrow and long foundation pit in the excavation process. On the basis of reading a large number of relevant literatures at home and abroad and summarizing the relevant research results, this paper takes Harbin-Mudanjiang Passenger Dedicated Line (Harbin-Mudanjiang Passenger Dedicated Line) Aimin tunnel exit open-cut section of the narrow deep foundation pit excavation in the excavation. Based on the field monitoring in the process of excavation, combined with theoretical analysis and three-dimensional numerical simulation analysis, the field construction is guided and the feedback design is carried out. At the same time, the force, deformation of the retaining structure and the influence of excavation on the surrounding environment in the process of excavation are preliminarily discussed. The main contents and related conclusions are as follows: (1) Through on-site monitoring, it is known that during the whole process of foundation pit construction, the amount of monitoring items has not reached the alarm value, and the retaining structure works normally. The maximum horizontal displacement of pile body reaches 13.72 m m in the whole process of exposed floor construction, which is located at the position of 8.0 m downward from the top of pile between bracing piles. With the increase of the maximum position, the maximum value is about 7.0 m from the top of pile when excavated. The maximum bending moment of pile body also occurs on the pile between bracing piles, the maximum value is 464.0 kN.m, and the pile top. The bending bearing capacity of the normal section is far from 1410kN.m. The reason is that a certain amount of horizontal displacement occurs at the top and bottom of the pile, which is bound to release the internal force of the retaining pile. The maximum horizontal displacement obtained by the code method is 16.78 mm. The location of the maximum displacement is consistent with that obtained by the three-dimensional finite element analysis. It occurs about 7.5 meters from the pile top. The maximum displacement measured by the field is slightly downward and located 8.0 meters to the left of the pile top. For the pile bending moment, the maximum value of the three-dimensional finite element analysis is 883.1 kN.m, the maximum value of the code method is 966.5 kN.m, but the field measurement results are much smaller, the maximum value is only 464.0 kN.m, which is caused by internal release; the internal force and deformation of the crown and beam are close to the trend of the three methods. (3) In order to evaluate the foundation comprehensively. The stability of the pit is estimated by empirical formula and three-dimensional finite element analysis. The maximum ground settlement is 10.7 mm from the top of the pile and 6.9 m from the top of the pile. 10.2 mm, the maximum value of pit bottom uplift obtained by three-dimensional finite element analysis is 12.1 mm, occurring about 1.0 m away from the retaining structure. (4) In all optimization schemes, changing the length of anchorage section has the least influence on the stress and deformation of the retaining structure; changing the diameter of the pile has the most severe influence on the retaining pile and the transverse brace, when the diameter of the pile decreases from 1.0 m to 0.7 m, the horizontal displacement is the smallest. The maximum value is 28.0m m, which is very close to the warning value of 30m M. The bending moment of pile body has reached 85.4% of the bearing capacity of normal section moment of pile body. At this time, the bending moment of transverse bracing has increased by 139% compared with the original model, and has exceeded the bending capacity of normal section of transverse bracing by 815kN.m. Finally, a design scheme of envelope structure suitable for construction according to site construction procedure is put forward, which is economical and reasonable on the premise of ensuring construction safety.
【學位授予單位】:蘭州交通大學
【學位級別】:碩士
【學位授予年份】:2017
【分類號】:U455

【參考文獻】

相關期刊論文 前10條

1 任建喜;王東星;王江;劉康輝;程遠;張楊洋;劉東洋;;全蓋挖法地鐵車站基坑及周邊變形規(guī)律研究[J];鐵道工程學報;2016年05期

2 丁樂;;基坑開挖對鄰近地鐵車站安全影響的三維有限元分析——以西朗公交樞紐站為例[J];隧道建設;2015年04期

3 陳健;;膨脹土中狹長型深基坑圍護結構受力變形分析[J];地下空間與工程學報;2015年02期

4 吳兵;陳樂意;周立;;考慮空間效應的基坑變形數值分析[J];南昌航空大學學報(自然科學版);2015年01期

5 左殿軍;史林;李銘銘;紀文棟;;深基坑開挖對鄰近地鐵隧道影響數值計算分析[J];巖土工程學報;2014年S2期

6 連寶琴;胡斌;王新剛;劉飛;余宏明;;武漢地鐵名都車站基坑開挖監(jiān)測與數值分析[J];長江科學院院報;2014年05期

7 梁志松;;深基坑三維應力場和滲流場耦合分析與模擬[J];長江科學院院報;2014年05期

8 周勇;郭楠;朱彥鵬;;蘭州地鐵世紀大道站基坑支護監(jiān)測與數值模擬[J];鐵道工程學報;2014年01期

9 朱炎兵;周小華;魏仕鋒;譚勇;;臨近既有地鐵車站的基坑變形性狀研究[J];巖土力學;2013年10期

10 李磊;段寶福;;地鐵車站深基坑工程的監(jiān)控量測與數值模擬[J];巖石力學與工程學報;2013年S1期

相關會議論文 前1條

1 褚峰;李永盛;梁發(fā)云;李彥東;;土體小應變條件下緊鄰地鐵樞紐的超深基坑變形特性數值分析[A];第十一次全國巖石力學與工程學術大會論文集[C];2010年

相關博士學位論文 前1條

1 劉濤;基于數據挖掘的基坑工程安全評估與變形預測研究[D];同濟大學;2007年

相關碩士學位論文 前10條

1 孫豫;地鐵車站基坑穩(wěn)定性及變形特性研究[D];東華理工大學;2016年

2 黃立本;華東地區(qū)某市地鐵深基坑變形規(guī)律研究[D];蘭州交通大學;2016年

3 張杰;青島地鐵保兒站深基坑變形特征研究[D];山東大學;2015年

4 傅震;黃土地區(qū)地鐵車站深基坑變形規(guī)律的分析[D];長安大學;2014年

5 董格;地鐵深基坑監(jiān)測與復挖數值模擬方法研究[D];武漢理工大學;2014年

6 趙延;地鐵車站深基坑開挖對臨近建筑物影響的監(jiān)測及數值模擬研究[D];石家莊鐵道大學;2014年

7 李賀龍;朝陽公園地鐵車站基坑開挖的變形規(guī)律研究[D];中國地質大學(北京);2013年

8 周坤鵬;強蠕變性軟土地鐵基坑施工變形特性研究[D];上海交通大學;2013年

9 任俐璇;青島地鐵明挖車站深基坑支護監(jiān)測分析及穩(wěn)定性研究[D];山東大學;2012年

10 任拴院;南京地鐵車站深基坑變形規(guī)律現場監(jiān)測研究[D];西安科技大學;2012年

,

本文編號:2249034

資料下載
論文發(fā)表

本文鏈接:http://sikaile.net/kejilunwen/daoluqiaoliang/2249034.html


Copyright(c)文論論文網All Rights Reserved | 網站地圖 |

版權申明:資料由用戶59217***提供,本站僅收錄摘要或目錄,作者需要刪除請E-mail郵箱bigeng88@qq.com