頂管工作井開挖支護及頂進過程的數值模擬分析
本文選題:頂管工作井 + 數值模擬; 參考:《石家莊經濟學院》2015年碩士論文
【摘要】:頂管工作井是安放頂進設備的場所,也是掘進機和工具管的始發(fā)地,同時又是承受主頂油缸反作用力的構筑物。頂管工作井的安全和穩(wěn)定,關系到整個頂管施工的成敗,因此頂管工作井的支護設計就顯得尤為重要。本文以“南水北調配套工程”為依托,并選取第一單元中的“唐望干管輸水管線穿越蠡野線工程”為背景,通過對頂管工作井開挖支護及頂進的數值模擬,分析頂管施工對支護結構的影響,以及頂進施工引起的地面沉降。具體內容如下:1.依據規(guī)范要求,對頂管工作井的開挖支護進行設計,采用有限元法對頂管工作井的支護開挖進行模擬,研究其受力和變形特點,驗證支護方案的可行性。2.根據計算結果得出,隨著工作井開挖深度的加深,工作井的水平位移和豎向位移逐漸加大,且水平位移最大值基本位于-13m的黏土層內。3.研究工作井承受橫向頂力階段的受力和變形,并與開挖支護階段相對比,分析頂進力施加對工作井的影響。4.通過數值模擬分析橫向頂力施加階段的垂直位移,得出在頂進方向的垂直剖面上,地面沉降表現出“中間大兩頭小”的規(guī)律。
[Abstract]:The pipe-jacking working well is the place where the jacking equipment is placed, the starting place of the roadheader and the tool pipe, and the structure which bears the reaction force of the main top oil cylinder at the same time. The safety and stability of the pipe-jacking working well is related to the success or failure of the whole pipe-jacking construction, so the support design of the pipe-jacking working well is particularly important. Based on the "South-to-North Water transfer supporting Project" and the "Tangwang main Water Pipeline Project through the Liye Line" in the first unit, the numerical simulation of the excavation, support and jacking of the pipe-jacking working well is carried out in this paper. The influence of pipe jacking construction on supporting structure and the ground subsidence caused by jacking construction are analyzed. The details are as follows: 1. According to the specification, the excavation support of pipe-jacking working well is designed. The finite element method is used to simulate the excavation of pipe-jacking working well. The characteristics of force and deformation are studied, and the feasibility of supporting scheme is verified. According to the calculation results, the horizontal displacement and vertical displacement of the working well are gradually increased with the deepening of the excavation depth of the working well, and the maximum horizontal displacement is basically located in the clay layer of -13 m. This paper studies the stress and deformation of the working well in the stage of bearing transverse top force, and compared with the stage of excavation and support, analyzes the influence of jacking force on the working well. Through numerical simulation and analysis of vertical displacement in the stage of lateral top force application, it is concluded that in the vertical section of the thrust direction, the land subsidence shows the law of "big and two ends in the middle".
【學位授予單位】:石家莊經濟學院
【學位級別】:碩士
【學位授予年份】:2015
【分類號】:TU990.3;TU753
【參考文獻】
相關期刊論文 前10條
1 王漢席;高尚;于海俠;尹偉;徐建玲;;軟弱土層中工作井受力分析及加固處理措施[J];給水排水;2015年03期
2 陶炳芳;;濕陷性黃土地區(qū)超深頂管工作井支護施工技術研究[J];城市道橋與防洪;2013年11期
3 黃堅生;;矩形頂管工作井穩(wěn)定性三維數值模擬[J];低溫建筑技術;2013年05期
4 麻冬敏;王萌;;深基坑變形的影響因素[J];科技信息;2012年05期
5 余田喜;沈海琴;;論頂管工作井及接收井的基坑支護結構選型[J];廣東科技;2009年16期
6 滕俊剛;;頂管工作井的結構選型與應用[J];市政技術;2009年S1期
7 李國強;李懷珍;韓平;;河北省南水北調配套工程合理高效利用土地資源的思考[J];南水北調與水利科技;2008年S2期
8 賀桂成;丁德馨;;頂管工作井圍護開挖過程的FLAC~(3D)模擬[J];南華大學學報(自然科學版);2008年03期
9 陳育民;劉漢龍;;鄧肯-張本構模型在FLAC~(3D)中的開發(fā)與實現[J];巖土力學;2007年10期
10 劉井學;陳有亮;陳劍亮;;某深基坑開挖的三維有限元模擬與分析[J];建筑結構;2007年06期
相關碩士學位論文 前6條
1 雷晗;大直徑砼頂管工程中土與結構的相互作用分析[D];上海交通大學;2012年
2 孫兆興;基于數值模擬的頂管井基坑穩(wěn)定性分析[D];西南交通大學;2009年
3 余芳;頂管施工引起地面沉降的分析研究[D];上海交通大學;2009年
4 鄭學鑫;抗滑樁樁間土拱效應及其有限元模擬研究[D];河海大學;2007年
5 賀桂成;深基坑圍護開挖土與支護結構相互作用穩(wěn)定性研究[D];西安科技大學;2005年
6 吳修鋒;頂管施工引起的地層移動與變形控制研究[D];南京工業(yè)大學;2004年