某核電站閉式冷卻水泵電機(jī)軸承異響故障分析
[Abstract]:In view of the abnormal noise of motor bearing during the operation of a conventional island cooling pump in a nuclear power station, the disassembly of the motor was carried out through field inspection and analysis to determine that the bearing clearance was too large. The main reason is that the foreign body enters the bearing and the grease storage space in the bearing chamber is small. After changing the bearing clearance at the motor drive end from the original C3 group to the ordinary group, the control of bearing cleanliness is strengthened and the bearing room is filled with grease, the problem of abnormal noise of the bearing can be solved.
【作者單位】: 中廣核工程有限公司設(shè)備采購(gòu)與成套中心;
【分類(lèi)號(hào)】:TM623;TH133.3
【相似文獻(xiàn)】
相關(guān)期刊論文 前10條
1 李少魁;合理選擇電機(jī)軸承游隙的初步探討[J];軸承;1984年05期
2 張衛(wèi)軍,陳曙,楊萍;提高微型軸承游隙測(cè)量準(zhǔn)確度的方法[J];軸承;2000年09期
3 邱年寶;軸承游隙的計(jì)算與測(cè)量技術(shù)在冷鋸主軸中的應(yīng)用[J];機(jī)械工程師;2002年06期
4 張永紀(jì);;軸承游隙的選擇[J];通用機(jī)械;2007年01期
5 文毫;;巧妙提高軸承游隙測(cè)量精度[J];現(xiàn)代班組;2009年02期
6 彌紅斌;楊文利;;有關(guān)影響軸承游隙因素的分析[J];機(jī)械工程師;2011年01期
7 周錦城;;淺談?shì)S承游隙[J];內(nèi)燃機(jī)車(chē);1987年04期
8 耕田;197726型貨車(chē)軸承游隙不合格的原因分析[J];鐵道車(chē)輛;1989年02期
9 劉晶紅,,丁浩;數(shù)字式軸承游隙測(cè)量?jī)x[J];光學(xué)精密工程;1995年01期
10 王正君,徐一春,張善青;機(jī)床主軸滾動(dòng)軸承游隙組的選擇計(jì)算[J];機(jī)床與液壓;2002年03期
相關(guān)會(huì)議論文 前1條
1 彌紅斌;楊文利;;有關(guān)影響軸承游隙因素的分析(摘要)[A];2010全國(guó)機(jī)電企業(yè)工藝年會(huì)《上海電氣杯》征文論文集[C];2010年
相關(guān)重要報(bào)紙文章 前2條
1 韓云峰;巧妙提高軸承游隙測(cè)量精度[N];中國(guó)電力報(bào);2008年
2 易水洪 鄧明旭;維修保養(yǎng)缺位 纜車(chē)脫軌[N];中國(guó)安全生產(chǎn)報(bào);2009年
本文編號(hào):2427116
本文鏈接:http://sikaile.net/kejilunwen/jixiegongcheng/2427116.html