慶鐵線擴能安全改造工程后評價研究
[Abstract]:Post-project evaluation occupies an important position in the whole project cycle. The domestic industries pay more and more attention to the post-project evaluation, and strengthen the research and application of the theory and method of post-project evaluation. In order to improve the project management level and investment income of the project, CNPC put forward the requirements of post-project evaluation. However, in the current petroleum enterprises, many enterprises carry out the post-project evaluation work is simplified post-evaluation, there is no in-depth analysis and evaluation of the project. The purpose of this paper is to set up a complete evaluation index system of Qingtie railway line expansion safety reconstruction project, and then to carry out detailed post-evaluation and find out the problems, taking the Qingqing railway line capacity expansion safety reconstruction project as an example. It can be used for reference in the later stage of pipeline construction. On the basis of deep research on the relevant theory of post-evaluation work, combined with the actual situation of the QingyingRailway line capacity expansion and reconstruction project, this paper constructs the post-evaluation index system of the QingyingRailway line expansion safety reconstruction project. In the post-evaluation index system of the project, five primary evaluation indexes, namely, pre-work, construction implementation, production operation, investment and financial benefit, impact and sustainability, are set. Several secondary evaluation indexes are set up under each evaluation index, and the weight of each index is determined by using the analytic hierarchy process (AHP). Based on the post-evaluation index system of Qingtie railway line capacity expansion and reconstruction project, this paper makes a detailed post evaluation on the Qingtie railway line expansion safety reconstruction project. The fuzzy comprehensive evaluation method of degree of success is applied to the comprehensive post-evaluation of the project of capacity expansion and reconstruction of Qing-tie railway line. Based on the analysis of the post-evaluation results, this paper summarizes the problems existing in the development, construction and operation of the Qingqing Railway Line's capacity expansion and transformation project, extracts the representative problems, and provides a reference for the later construction of pipeline engineering. Thus, the investment income of pipeline engineering is improved.
【學位授予單位】:中國石油大學(華東)
【學位級別】:碩士
【學位授予年份】:2015
【分類號】:TE973
【參考文獻】
相關期刊論文 前10條
1 段云龍;周靜斌;申曉靜;;基于熵權TOPSIS法的房地產項目后評價模型研究[J];項目管理技術;2011年09期
2 孫慧;范志清;孫曉鵬;;基于模糊綜合評價的BOT高速公路建設項目后評價[J];統(tǒng)計與決策;2011年04期
3 牛東曉;李建青;;基于物元可拓模型的火電廠建設項目過程后評價研究[J];華北電力大學學報(自然科學版);2010年06期
4 高軍;高穎;;對成品油銷售網絡投資項目后評價指標體系構建的探討[J];國際石油經濟;2010年07期
5 方興君;趙連增;杜敏;高軍;丁世強;;對改進投資項目后評價方法體系的探討[J];國際石油經濟;2010年04期
6 黃旭楠;李華啟;王錫柱;;油氣勘探項目后評價指標體系與定量化評價[J];國際石油經濟;2010年01期
7 杜靜;;對汶川震后恢復重建項目后評價工作的探討[J];科技進步與對策;2009年21期
8 關永;蹇瑞紅;劉景武;;項目后評價工作實踐探討[J];當代化工;2009年03期
9 丁海潮;陳惠玲;管殿聆;張偉;;城市基礎設施建設項目施工階段后評價及案例分析[J];建筑經濟;2009年04期
10 王尊先;;基于成功度綜合評價模型的水電工程施工后評價[J];南水北調與水利科技;2008年05期
相關博士學位論文 前1條
1 楊文升;油氣田產能建設項目后評價研究[D];哈爾濱工程大學;2009年
相關碩士學位論文 前5條
1 張程;東北電力市場試點項目的后評價研究[D];華北電力大學(北京);2010年
2 王寶光;LB地區(qū)原油勘探項目技術經濟后評價研究[D];吉林大學;2010年
3 高芳;中石大青島校區(qū)一期工程建設項目后評價研究[D];中國石油大學;2009年
4 文俊;青龍路加油站工程建設項目后評價[D];重慶大學;2008年
5 趙雪;高速公路項目過程后評價研究及應用[D];南京航空航天大學;2007年