土體加筋技術(shù)在站場高填方邊坡工程中的應(yīng)用
發(fā)布時(shí)間:2018-02-28 18:48
本文關(guān)鍵詞: 站場 高填方邊坡 土體加筋 土工織物 設(shè)計(jì)技術(shù) 穩(wěn)定性 出處:《油氣儲運(yùn)》2017年05期 論文類型:期刊論文
【摘要】:在管道工程建設(shè)過程中,由于站場選址受限,出現(xiàn)了許多高填方邊坡工程,站場施工前必須先對填方邊坡進(jìn)行處理,使其滿足穩(wěn)定性要求后再進(jìn)行后續(xù)站場施工。云南成品油安寧首站場區(qū)處于填方工程中,最大填方高度30 m,填方區(qū)布設(shè)油罐和管道,處理要求高,通過對比坡率方案、抗滑樁方案及土工布加筋方案的優(yōu)缺點(diǎn),最終確定采用土工布加筋方案進(jìn)行邊坡處理。介紹了該填方邊坡的設(shè)計(jì)思路、計(jì)算過程及施工要求,通過現(xiàn)場實(shí)際應(yīng)用,取得了良好的經(jīng)濟(jì)效益和社會(huì)效益,可為后續(xù)類似工程的建設(shè)提供有益的借鑒。
[Abstract]:In the process of pipeline construction, because the station is limited, there are many high fill slope station, must fill slope processing field before construction, to meet the stability requirements after subsequent field construction. Yunnan Oil Station District in the first peace filled square project, the maximum height of the embankment is 30 m, filling tank and pipeline layout, processing requirements, scheme by comparing the ratio of slope, the advantages and disadvantages of the anti slide pile scheme and geotextile reinforcement scheme, and ultimately determine the use of geotextile reinforcement scheme of slope treatment. This paper introduces the design ideas of the embankment slope, the calculation process and construction requirements, through the actual application and achieved good economic and social benefits, can provide a useful reference for the future construction of similar projects.
【作者單位】: 中國石油管道局工程有限公司設(shè)計(jì)分公司;
【基金】:中國石油天然氣管道局推廣應(yīng)用項(xiàng)目“土工合成材料在油氣管道工程中的應(yīng)用技術(shù)研究”,TG15-4-A
【分類號】:TE973
,
本文編號:1548510